PG&E Tri-Valley 2002 Capacity Increase Project
Under contract with the CPUC, Aspen prepared a Notice to Proceed with
construction for CPUC review and monitored construction of an
underground 230 kV transmission line in the south Livermore and Pleasanton
areas. The project as approved by CPUC (based on the EIR prepared by Aspen)
includes approximately 2.5 miles of 230 kV overhead dual-circuit
transmission line, 11.8 miles of underground line, construction of two new
230 kV substations (in Livermore and Dublin), and modification of an
existing station (Pleasanton).
|
|
|
|
Services Provided on this Project:
• Environmental Impact Analysis
• Mitigation Monitoring
• Electromagnetic Fields
• Land Use
• Geology
• EMF and Underground Transmission Issues
• Transmission Planning
• Biology
• Traffic & Transportation
• Water Resources
• Cultural Resources
• Visual Resources
• Public Participation
|
|
|