Williams Communications Sentry Marysville Project

Under contract to the California Public Utilities Commission (CPUC), Aspen monitored the construction of the Williams Communications Sentry Marysville Project. Construction activities consisted of: (1) the installation of approximately five miles of new underground conduit and fiber optic cable (including tie-ins and manhole installation); and (2) connecting Williams to existing Qwest and SBC networks within Yuba and Butte Counties. In implementing the Mitigation Monitoring Program for this project, Aspen reviewed pre-construction compliance materials, prepared a recommended Notice to Proceed with Construction for CPUC consideration, monitored construction and compliance activities, prepared and submitted Weekly Reports to CPUC, and reviewed and prepared recommended decisions on Variance Requests.

Practice areas: Infrastructure and Public Works

Services provided for this project: